Malone Group completed a capacity increase project for a brewer with a total project cost of approx £2.5. The scope consisted of:

  • Increase capacity to packaging around site space constraints
  • Upgrade all BBT valve infrastructure to current hygienic design standards
  • Increase DAL capacity
  • Replace obsolete control system
Malone Group was responsible for the following phase of work:
  • Replacement of all BBT valve
  • anifolds during 8 day shutdown
  • Design and implementation of high accuracy blending system ±0.05% ABV
  • Re-use of BBT’s as high gravity and blending direct to packaging lines